The following Special Conditions of Contract (SCC) shall supplement the General Conditions of Contract (GCC). Whenever there is a conflict, the provisions herein shall prevail over those in the GCC.
|
GCC clause
reference |
Special Conditions
of Contract |
|
|
The Procurement Reference Number is: |
|
GCC 1.1 |
The Eligible Countries are those listed in Section 5 of the Request for Proposals document. The Member in Charge is: |
|
GCC 3.1(d) |
Other documents forming part of the
contract are: |
|
|
|
|
|
|
|
GCC 6.1 |
The addresses for Notices are: for the Procuring Entity: Street Address: Floor/Room number: Town/City: Postal Code/PO Box No: Country: Telephone: Facsimile number: Email: For the Supplier: Street Address: Floor/Room number: Town/City: Postal
Code/PO
Box No: Country: Telephone: Facsimile number: Email: |
|
GCC 8.1 |
The Authorised Representatives are: For the Procuring Entity: For the Supplier: |
|
GCC 9.1 |
The Supplier, Sub-consultants, and their Personnel shall pay such taxes, duties, fees, and other impositions as may be levied under the law of the Federal Democratic Republic of Ethiopia. |
|
GCC 12.1 |
The period within which the Services shall have commenced is: |
|
GCC 13.1 |
The period for expiration of the contract is: |
|
GCC 18.3(b) |
The following activities are prohibited: |
|
GCC 20.1 |
The risks and coverage shall be: (i) Third Party motor vehicle (ii) Third Party liability (iii) Employer’s liability and workers’ compensation (iv) Professional liability (v)
Loss or damage to equipment and property (vi)
Other |
|
GCC 21.1(c) |
The Procuring Entity’s prior approval is also required for: |
|
GCC 23.1 |
The future use of documents is
restricted as follows: |
|
GCC 26.1(g) |
The Procuring Entity shall provide the following further assistance: |
|
GCC 27.1 |
Any change in laws or regulations shall not result in any change to the period for completion of the services or the Contract Price. |
|
|
|
|
GCC 30.2 |
The Contract is a __________ contract. |
|
GCC 32.3 |
Personnel time shall include time for necessary travel. |
|
GCC 32.5 |
The Supplier’s total remuneration shall not exceed: |
|
GCC 33.1 |
The payment schedule shall be: |
|
GCC 33.2 |
An Advance Payment Guarantee shall be required. The period of validity of the Advance Payment Guarantee shall be: |
|
GCC 34.1 |
Payment shall be made by the Procuring Entity within _____ days of receipt of the request for payment [and within _____ days in the case of the final payment]. |
|
GCC 34.2 |
The following documentation shall be required to support requests for payment: |
|
GCC 34.4 |
Interest shall be paid on late payments at the rate of: |
|
GCC 35.1 |
Prices
charged by the Supplier shall not vary from the prices quoted in the
Contract. |
|
GCC 37.1 |
The formal mechanism for dispute settlement shall be: |